There were some little holes to be filled in like the areas around the tubes from the ERV.
Looks like I will have sand left over as well but that can be used for the base for the RainWater Tank or for the inside rock wall...won't be wasted.
More cleaning up going on and finishing the little gable.
Fred who did the install of the rough out for the central whole house vacuum system. Fred was also the supervisor for the foundation and dry-in phases of the construction.
The white 2 inch pipe is the vacuum system. I had only a need for two inlets on low 24 voltage and will tie them to a regular shop vac with a relay for the outlet and a transformer from 110v to 24v. The shop vac will be in the Mechanical Room in the Garage.
Fred is bringing the line into the Garage. Notice the fuse panel on the wall, it is in backwards but turned out to be a good idea since that cleared the area to store the shop vac on the other side of the wall in the Mechanical Room. Some things do work out for the best.